The Tri-Cities HS Performing Arts Wing was evaluated and determined to be undersized in program area, and net building area. The as-built (existing) conditions at Tri-Cities were compared with the North Springs High School Performing Arts program and the 2005 Educational Specifications. Several options/alternatives for expansions and/or additions were developed that would accommodate program increases/improvements as needed. After evaluation it was decided that a free standing building was the preferred option, best suited for this site.

Performing Arts Building: (18,880 gross sq. ft.)

This new building addition will house the Band, Choral, Orchestral areas, and 2 Dance Studios with associated spaces.

Interior Renovations: (5,723 net sq. ft.)

Portions of the existing Tri-Cities HS music and drama areas will be renovated per the attached plan. The proposed renovated area will include 2 Offices, Storage, a Drama Classroom, Practice Rooms, and a Black Box Theater. The conceptual planning work has been completed and is ready for approval so the project can proceed into the design phase.

Infrastructure & Local School Needs:

The SPLOST III budgeted Infrastructure and Local School Needs work will be completed at the same time, along with the Performing Arts Building and Interior Renovation work.

The projected budget for this project is as follows:

Tri-Cities High School Performing Arts Building (New 18,880 SF + Renovated 5,723 SF) and the Infrastructure and Local School Needs.

TriCities Reroofing of auditorium with a scheduled completion date of December 2008.